Featured Project

550,000 SF Soil Stabilization for PGA of America in Frisco, TX

When it comes to golf, the stakes don't get any higher than the PGA. While it's easy to watch the captivating drama of the world's most talented golfers going head-to-head, it's also easy to overlook how much planning, preparation, and hard work go into ensuring every golf tournament meets the PGA's highest standards. And after working directly with the renowned sports organization firsthand, nobody knows that hard work better than Universal Soil Stabilizers! 

The PGA needed a vendor compound built in Frisco, Texas, ahead of the 2027 PGA Championship across the street, and the ground under it was expansive North Texas clay. Before any paving or gravel could go down, that clay had to be mitigated across the full 550,000-square-foot footprint.

The compound was planned as a combination of roadways, pavement, and gravel parking — flatwork that sits directly on the subgrade and feels every seasonal moisture swing. Universal Soil Stabilizers was brought in to treat the clay in place, and the assignment grew from injection into a broader coordination role spanning the geotechnical firm, the environmental company, the architect, the engineering firm, and PGA of America itself.

Key Takeaways

  • THE CHALLENGE
    Expansive clay had to be treated beneath 550,000 square feet of planned roadways, pavement, and gravel parking on a schedule tied to a national event.
  • THE INJECTION
    Four tractor rigs — five near the end — injected the proprietary chemical soil-stabilization solution on staggered passes to the recommended treatment depth across every mapped section.
  • THE RESULT
    Post-injection cores were tested section by section until the full site met the required values and the next contractor could mobilize.

Frisco sits in a part of the metroplex where expansive clay routinely drives mitigation requirements, and our Dallas-Fort Worth soil stabilization crews work in it regularly. Preparation alone ran a couple of months before the first rig turned a wheel.

Flatwork of this size lives or dies on subgrade consistency, and the project team wanted the clay addressed in place rather than through broad excavation and replacement across half a million square feet. Chemical injection let us treat the active soil zone below grade while the compound layout was still being surveyed and staked.

We also carried the surrounding scope under our Turn-Key soil stabilization approach, including water logistics, stormwater compliance, subcontracted dirt work, and direct coordination with the geotechnical firm, so the owner had one point of contact for soil mitigation.

Project Summary

Client Profile: PGA of America 
Project Location: Frisco, Texas (Dallas–Fort Worth)
Primary Objective: Mitigate expansive clay across the entire 550,000-square-foot compound before flatwork, using commercial soil stabilization methods suited to pavement and parking areas.
Injection Method: In-place chemical injection delivered by tractor-rig injections, with staggered passes across each mapped section.
Key Outcome: Every section reached its required values after testing and reinjection, and the pad was turned over to the following contractor.

Phase One: Treating the Treacherous North Texas Clay

Our review started with the site's geotechnical information and the compound layout: roadways, a sizable amount of pavement, and gravel parking spread across 550,000 square feet. The clay beneath all of it needed treatment, which meant the injection grid had to cover the entire footprint rather than a handful of building pads. We contracted directly with the geotechnical firm, so sampling kept pace with production, and the testing plan called for a bore roughly every 20,000 square feet.

Field conditions were not uniform. Parts of the site held gravel streams and areas where a lot of crushed gravel had been filled in, and those zones fight saturation, meaning the solution follows the path of least resistance through the rock instead of working into the clay around it. We flagged them early, knowing they would need extra attempts, and we kept the survey team coming back to mark posts so the injection limits were clear before each section opened up.

Phase Two: Running Five Rigs in Frisco

The treatment was delivered with customized masts on skid steers tied to a pump trailer and a high-pressure water source, typically a fire hydrant. Injection holes were set on three-foot centers, then staggered on subsequent passes until spacing worked out to roughly a foot apart, and the rods stopped every 12 to 18 inches on the way down and held until full refusal.

Saturating clay is like watering a house plant: one pass is never the whole job, so crews went back over each section until the soil column was treated from the topsoil down to the recommended depth of about 10 feet. Four tractors ran for most of the two months of injection, and a fifth joined near the end to hold the timeline.

"There's a lot of that goes into the protocol that the injection company has to follow. Testing, site prep, making sure that the stakes and the bores are coming out of the right locations, and so much more. But in the end, we were able to get it exactly where they needed it so that the next contractor could come in and do their job." - (Sara, Universal Soil Stabilizers)

We also served as the general contractor for a stretch of the work. That meant maintaining the stormwater permits and best management practices, submitting weekly inspections to the Frisco stormwater inspector, and subcontracting the dirt work and silt fencing to companies we have worked alongside for years.

Phase Three: Passing Results, Section by Section

After a 48- to 72-hour cure window, cores were drilled and delivered to the lab for swell testing against the project's required values. We tracked the site on an aerial map broken into named sections, logging the injection date, the drill date, the test date, and the pass or fail result for each one. The gravel-filled areas behaved exactly as expected and took two, and in some spots three, attempts before the numbers came in where they needed to be.

Reinjection is never a surprise, and any contractor claiming a perfect pass rate is worth second-guessing. Section by section, the map went green, the documentation went to the engineering team, and the compound was handed off so the following contractor could start building. For a project tied to a fixed event date, having verified soil data in hand at turnover mattered as much as the treatment itself.

Planning Soil Mitigation in Frisco, TX? Trust Universal Soil Stabilizers! 

At Universal Soil Stabilizers, we have been treating expansive clay for Texas builders, developers, and general contractors since 2012, on everything from single lots to large commercial flatwork. We work from your geotechnical report, run the injection, coordinate the post-injection testing through licensed geotechnical partners, and get the results back to your engineer.

Have a pad, parking area, or roadway in Frisco that needs the clay addressed before construction? Request a bid, and we will review your report and site plans.

Universal Soil Stabilizers
Lovelady, Texas 75851
Call 830-358-3804 or Schedule Online

Frequently Asked Questions

Can chemical soil injection treat pavement and parking areas in Frisco, TX?

Yes. On this Frisco vendor compound, the treated area was roadways, pavement, and gravel parking rather than building pads. Flatwork sits directly on the subgrade, so reducing the clay's moisture-driven swell potential before paving is a common application in the Dallas–Fort Worth area.

How long does soil stabilization take on a 550,000-square-foot site?

The injection phase on this project ran about two months with four tractor rigs, and a fifth rig was added near the end to meet the schedule. Preparation — permits, subcontractors, survey, and geotechnical coordination — took a couple of months before mobilization. Duration depends on square footage, treatment depth, and site conditions.

What happens if a post-injection swell test fails?

The section is reinjected and retested. On this site, areas filled with crushed gravel resisted saturation and needed two or three attempts before meeting the required values. Every injection, drill, test, and reinjection date is tracked by section so the builder and the engineer always know where the site stands.