Featured Project 20-Lot Chemical Soil Injection After Failed Moisture Checks in Temple, TX Moisture conditioning has a shelf life. On a production subdivision east of I-35 in Temple, Texas, that window had closed on lots still waiting for home starts, and the project's geotechnical firm needed current soil data before anyone formed a slab. Universal Soil Stabilizers was brought in by the geotechnical firm working the subdivision for D.R. Horton, one of the largest production builders in the country. Our scope started as moisture conditioning checks (MC checks) pulled with our drill rig and delivered to the lab. The site is old farmland in north central Temple, with larger pad and lot sizes than a typical Central Texas subdivision. Once the lab numbers came back, the conversation moved from testing to mitigation. Key Takeaways THE CHALLENGE The moisture conditioning window on a group of graded lots had lapsed, and retesting showed several pads still carried swell issues ahead of foundation work. THE TREATMENT We treated roughly 20 lots in place with tractor-rig chemical soil injection instead of re-excavating finished pads. THE RESULT The injection run took about three weeks, cores reached the lab within days of each pass, and about 80% of the lots have since been built on. When MC checks come back with swell issues at that stage of a development, the math changes. Re-excavating and re-conditioning the lots, or bringing in select fill a second time, would have meant moving dirt on pads that were already graded and ringed by finished streets and utilities. Here's how our chemical injections treated the clay below grade and left the pad where it is, making for a quicker and more cost-effective route at that point in the schedule. Project Summary Client Profile: Geotechnical engineering firm working a D.R. Horton production subdivision Project Location: Temple, Texas — Central Texas, east of I-35 Primary Objective: Retest moisture-conditioned lots and clear them for foundation work as part of our home builder soil services Injection Method: Drill-rig sampling for MC checks, followed by tractor-rig injections on roughly 20 lots Key Outcome: Lots released for home starts after lab testing; about 80% built on today First Things First: Moisture Conditioning Checks Geotechnical firms subcontract us for MC checks when a moisture-conditioned lot has aged past its window, generally about a year. After that time lapses, the geotech will require the builder to retest the lot and confirm the conditions have not changed. We mobilized the drill rig, pulled bore samples across the subdivision, bagged them, and delivered them to the lab. The lab identified a number of lots that failed their checks and still carried swell issues. Those pads could not move toward foundation work on the existing data, and the builder needed a path that fit the stage the development was already in. Injection kept the treatment below grade and the finished pads intact. Next Step: Tractor-Rig Injection On Failed Lots Treatment design starts with the geotechnical report. Depth, Potential Vertical Rise, and the lithology underneath tell us how to set our dilution rates and how to approach the clay. For this scope, we ran a tractor-rig setup: customized masts on skid steers tied to a pump trailer and a high-pressure water source, usually a fire hydrant meter, with the proprietary chemical soil-stabilization solution diluted at the pump and injected through the rods into the active zone, typically down to 10 feet. Both the soil and the access worked in our favor here. Old farmland in this part of Temple takes the injection well, without the rock and limestone layers that slow production in San Antonio and parts of Dallas-Fort Worth, and it sits in the same Central Texas clay belt we work for Waco soil stabilization projects. The pads were larger than average on this job, so each lot carried more square footage, but the ground itself gave us very few surprises. "We have a great working relationship with the geotech that was on this project and they have a great relationship with the builder as well. Samples were delivered within a reasonable amount of time, and results were provided to the builder promptly and everybody moved on their way." - (Matthew, Universal Soil Stabilizers) Coordination ran through the geotechnical firm lot by lot. Samples were at the lab two to three days after injection, and the firm reported results promptly to both our team and the builder. That three-way communication is the backbone of our Turn-Key soil stabilization scope and the way we run chemical soil injections on every subdivision we treat. The Conclusion: Verified Results & Seamless Build Out The injection work on this project ran about three weeks. Post-injection cores went to the lab shortly after each pass, and a swell report that comes back under 1% swell gives the geotech what it needs to sign off and release the lot. Testing in batches rather than waiting for the whole project kept reports moving back to the builder while we were still injecting. Home building followed behind the treatment. About 80% of the lots in that section now have houses on them, with a few still open. Treating the clay in place let the development hold its sequence instead of restarting earthwork on pads that were already graded and served by streets and utilities. Here for All Your Temple, Texas Soil Stabilization Needs! At Universal Soil Stabilization, we work both sides of this scope for Central Texas builders and geotechnical firms — pulling MC checks and core samples with our drill rig, and injecting the lots that come back short. Since 2012, we have treated single lots, full subdivisions, and commercial pads across Texas. Do you have lots in Temple that need retesting or soil mitigation before foundations go in? Send us the geotechnical report and site plan, and we will put a bid together! Universal Soil Stabilizers Lovelady, Texas 75851 Call 830-358-3804 or Schedule Online Frequently Asked Questions How long does moisture conditioning last on a Temple, TX lot? On this project, the window was about a year. Once that time lapses, the geotechnical engineer will typically require the builder to retest the lot with a moisture conditioning check to confirm the soil conditions have not changed. We pull those samples with our drill rig and deliver them to the lab handling the project. What happens when lots fail a moisture conditioning check? The builder and the engineer decide on a mitigation path for those specific lots. Once streets, utilities, and grading are already in, re-excavating for moisture conditioning or select fill is a heavy lift, so chemical soil injection often becomes the more practical option. On this Temple subdivision, we treated about 20 of the lots that came back with swell issues. How is the treated soil verified after injection? Core samples are drilled after the treatment has had time to cure and are tested by a licensed geotechnical lab. The lab runs a swell test against the project's required values, and the results go to the engineering team for review and sign-off. We track which lot each bore came from so the builder and the engineer always know what has been treated, tested, and released.